| 1 | AN ACT concerning State government.
| |||||||||||||||||||
| 2 | Be it enacted by the People of the State of Illinois,
| |||||||||||||||||||
| 3 | represented in the General Assembly:
| |||||||||||||||||||
| 4 | Section 5. The Green Buildings Act is amended by changing | |||||||||||||||||||
| 5 | Section 15 as follows: | |||||||||||||||||||
| 6 | (20 ILCS 3130/15)
| |||||||||||||||||||
| 7 | Sec. 15. Green Buildings Standards.
| |||||||||||||||||||
| 8 | (a) All new State-funded building construction and major | |||||||||||||||||||
| 9 | renovations of existing State-owned facilities are required to | |||||||||||||||||||
| 10 | seek LEED, Green Globes, or equivalent certification. | |||||||||||||||||||
| 11 | (b) All construction and major renovation projects, | |||||||||||||||||||
| 12 | regardless of size, must achieve the the highest level of | |||||||||||||||||||
| 13 | certification practical within the project budget. | |||||||||||||||||||
| 14 | (1) New buildings and major renovations of less than | |||||||||||||||||||
| 15 | 10,000 square feet must meet the highest standard of the | |||||||||||||||||||
| 16 | Leadership in Energy and Environmental Design's rating | |||||||||||||||||||
| 17 | system for new commercial construction and major | |||||||||||||||||||
| 18 | renovation projects, as established by the United States | |||||||||||||||||||
| 19 | Green Building Council, or an equivalent standard, | |||||||||||||||||||
| 20 | including, but not limited to, the Green Building | |||||||||||||||||||
| 21 | Initiative's Green Globes USA design program. USGBC LEED, | |||||||||||||||||||
| 22 | GBI Green Globes, or the equivalent certification is not | |||||||||||||||||||
| 23 | required. | |||||||||||||||||||
| |||||||
| |||||||
| 1 | (2) New buildings and major renovations of 10,000 | ||||||
| 2 | square feet or more must achieve the silver building rating | ||||||
| 3 | of the Leadership in Energy and Environmental Design's | ||||||
| 4 | rating system for new commercial construction and major | ||||||
| 5 | renovation projects, as established by the United States | ||||||
| 6 | Green Building Council, or an equivalent standard, | ||||||
| 7 | including, but not limited to, a two-globe rating in the | ||||||
| 8 | Green Globes USA design program. USGBC LEED, GBI Green | ||||||
| 9 | Globes, or the equivalent certification is required. | ||||||
| 10 | (c) Exemptions to these standards are buildings that are | ||||||
| 11 | not "comfort" conditioned as determined by the Board. However, | ||||||
| 12 | the project design team must document and incorporate all | ||||||
| 13 | appropriate sustainable building methods, strategies, and | ||||||
| 14 | technologies in the final design. | ||||||
| 15 | (d) State agencies and the project design team may apply to | ||||||
| 16 | the Board for a waiver from these standards. | ||||||
| 17 | (e) Waivers shall be granted by the Board or an appropriate | ||||||
| 18 | agency when the applicant can demonstrate and document:
| ||||||
| 19 | (1) An unreasonable financial burden, taking into | ||||||
| 20 | account the operating and construction costs over the life | ||||||
| 21 | of the building and the total cost of ownership of the | ||||||
| 22 | building. | ||||||
| 23 | (2) An unreasonable impediment to construction. | ||||||
| 24 | (3) The standards would impair the principal function | ||||||
| 25 | of the building. | ||||||
| 26 | (4) The standards would compromise the historic nature | ||||||
| |||||||
| |||||||
| 1 | of the structure. | ||||||
| 2 | Documentation on the submittal must include at a minimum: | ||||||
| 3 | (1) Life cycle cost analysis. | ||||||
| 4 | (2) Energy modeling. | ||||||
| 5 | The design team must provide the documentation for the new | ||||||
| 6 | project to confirm that LEED, Green Globes, or the equivalent | ||||||
| 7 | construction standards have been followed. | ||||||
| 8 | (f) In addition to any required LEED, Green Globes, or the | ||||||
| 9 | equivalent criteria, the Board shall require that all projects | ||||||
| 10 | referenced in subsection (a) implement at least one LEED | ||||||
| 11 | alternative transportation criterion for public transportation | ||||||
| 12 | or bicycle access. | ||||||
| 13 | (g) The green building standards contained in this Act | ||||||
| 14 | shall be analyzed and evaluated by the Board 5 years after the | ||||||
| 15 | effective date of this Act or upon the completion of 10 Board | ||||||
| 16 | green projects, whichever comes first.
| ||||||
| 17 | (Source: P.A. 96-73, eff. 7-24-09.)
| ||||||