     Amends the Illinois Procurement Code.  Removes the 2012 elimination of the Capital Development Board's authority to waive, under certain circumstances, the separate bid requirement for the 5 subdivisions of work with respect to construction contracts in excess of $250,000.  Effective immediately.
   |  
| 
 
 |  |  |  | 
 |  
|  |  
| 
|  | FISCAL NOTE ACT MAY APPLY |  |  |  |  |  
|    A BILL FOR |    | 
| 
   | 
| 
|  |  | SB3399 |  | LRB096 20469 JAM 36124 b |  | 
| 
 
   | 
| 1 |  |     AN ACT concerning finance.
  
 | 
| 2 |  |     Be it enacted by the People of the State of Illinois,
  | 
| 3 |  | represented in the General Assembly:
  
 
 | 
| 4 |  |     Section 5. The Illinois Procurement Code is amended  by  | 
| 5 |  | changing Section 30-30 as follows:
 
 | 
| 6 |  |     (30 ILCS 500/30-30)
 | 
| 7 |  |     Sec. 30-30. Contracts in excess of $250,000. For
building  | 
| 8 |  | construction contracts in excess of
 $250,000, separate  | 
| 9 |  | specifications shall be prepared for all
equipment, labor, and  | 
| 10 |  | materials in
connection with the following 5 subdivisions of  | 
| 11 |  | the work to be
performed:
 | 
| 12 |  |         (1) plumbing;
 | 
| 13 |  |         (2) heating, piping, refrigeration, and automatic
 | 
| 14 |  | temperature control systems,
including the testing and  | 
| 15 |  | balancing of those systems;
 | 
| 16 |  |         (3) ventilating and distribution systems for
 | 
| 17 |  | conditioned air, including the testing
and balancing of  | 
| 18 |  | those systems;
 | 
| 19 |  |         (4) electric wiring; and
 | 
| 20 |  |         (5) general contract work.
 | 
| 21 |  |     The specifications must be so drawn as to permit separate  | 
| 22 |  | and
independent bidding upon
each of the 5 subdivisions of  | 
| 23 |  | work.  All contracts awarded
for any part thereof shall
award  | 
|     | 
| 
|  |  | SB3399 | - 2 - | LRB096 20469 JAM 36124 b |  | 
| 
 | 
| 1 |  | the 5 subdivisions of work separately to responsible and
 | 
| 2 |  | reliable persons, firms, or
corporations engaged in these  | 
| 3 |  | classes of work.  The contracts, at
the discretion of the
 | 
| 4 |  | construction agency, may be assigned to the successful bidder  | 
| 5 |  | on
the general contract work or
to the successful bidder on the  | 
| 6 |  | subdivision of work designated by
the construction agency  | 
| 7 |  | before
the bidding as the prime subdivision of work, provided  | 
| 8 |  | that all
payments will be made directly
to the contractors for  | 
| 9 |  | the 5 subdivisions of work upon compliance
with the conditions  | 
| 10 |  | of the
contract.  A contract may be let for one or more  | 
| 11 |  | buildings in any
project to the same contractor.
The  | 
| 12 |  | specifications shall require, however, that unless the
 | 
| 13 |  | buildings are identical, a separate price
shall be submitted  | 
| 14 |  | for each building.  The contract may be awarded
to the lowest  | 
| 15 |  | responsible
bidder for each or all of the buildings included in  | 
| 16 |  | the
specifications.
 | 
| 17 |  |     The Until a date 3 years after the effective date of this  | 
| 18 |  | amendatory Act of the 95th General Assembly, the requirements  | 
| 19 |  | of this Section do not apply to a construction project for  | 
| 20 |  | which the Capital Development Board is the construction agency  | 
| 21 |  | if: (i) the project budget is at least $20,000,000; (ii) the  | 
| 22 |  | Capital Development Board has submitted to the Procurement  | 
| 23 |  | Policy Board a written request for a public hearing on waiver  | 
| 24 |  | of the application of the requirements of this Section to that   | 
| 25 |  | project, including its reasons for seeking the   waiver and why  | 
| 26 |  | the waiver is in the best interest of the State; (iii) the  | 
|     | 
| 
|  |  | SB3399 | - 3 - | LRB096 20469 JAM 36124 b |  | 
| 
 | 
| 1 |  | Capital Development Board has posted notice of the waiver  | 
| 2 |  | hearing on its procurement web page and on the online  | 
| 3 |  | Procurement Bulletin at least 15 working days before the  | 
| 4 |  | hearing;
(iv) the Procurement Policy Board, after conducting  | 
| 5 |  | the public hearing on the waiver request, reviews and approves  | 
| 6 |  | the request in writing before the award of the contract; (v)  | 
| 7 |  | the successful low bidder has prequalified with the Capital  | 
| 8 |  | Development Board; (vi) the bid of the successful low bidder  | 
| 9 |  | identifies the name of the subcontractor, if any, and the bid  | 
| 10 |  | proposal costs for each of the 5 subdivisions of work set forth  | 
| 11 |  | in this Section; and (vii) the contract entered into with the  | 
| 12 |  | successful bidder provides that no identified subcontractor  | 
| 13 |  | may be terminated without the written consent of the Capital  | 
| 14 |  | Development Board.
With respect to any construction project  | 
| 15 |  | described in this paragraph, the Capital Development Board  | 
| 16 |  | shall: (i) provide to the Auditor General an affidavit that the  | 
| 17 |  | waiver of the application of the requirements of this Section  | 
| 18 |  | is in the best interest of the State; (ii) specify in writing  | 
| 19 |  | as a public record that the project shall comply with the  | 
| 20 |  | disadvantaged business practices of the Business Enterprise  | 
| 21 |  | for Minorities, Females, and Persons with Disabilities Act and  | 
| 22 |  | the equal employment practices of Section 2-105 of the Illinois  | 
| 23 |  | Human Rights Act; and (iii) report annually to the Governor and  | 
| 24 |  | the General Assembly on the bidding, award, and performance. On  | 
| 25 |  | and after the effective date of this amendatory Act of the 95th  | 
| 26 |  | General Assembly, the Capital Development Board may award in  | 
|     | 
| 
|  |  | SB3399 | - 4 - | LRB096 20469 JAM 36124 b |  | 
| 
 | 
| 1 |  | each year contracts with an aggregate total value of no more  | 
| 2 |  | than $100,000,000 with respect to construction projects  | 
| 3 |  | described in this paragraph. | 
| 4 |  |     Until a date 5 years after the effective date of this  | 
| 5 |  | amendatory Act of the 94th General Assembly, the requirements  | 
| 6 |  | of this Section do not apply to the Capitol Building HVAC  | 
| 7 |  | upgrade project if (i) the bid of the successful bidder  | 
| 8 |  | identifies the name of the subcontractor, if any, and the bid  | 
| 9 |  | proposal costs for each of the 5 subdivisions of work set forth  | 
| 10 |  | in this Section, and (ii) the contract entered into with the  | 
| 11 |  | successful bidder provides that no identified subcontractor  | 
| 12 |  | may be terminated without the written consent of the Capital  | 
| 13 |  | Development Board.
  | 
| 14 |  | (Source: P.A. 94-699, eff. 11-29-05; 95-758, eff. 1-1-09.)
 
  | 
| 15 |  |     Section 99. Effective date. This Act takes effect upon  | 
| 16 |  | becoming law. 
  
 |