| 1 | AN ACT concerning finance.
| ||||||||||||||||||||||||
| 2 | Be it enacted by the People of the State of Illinois,
| ||||||||||||||||||||||||
| 3 | represented in the General Assembly:
| ||||||||||||||||||||||||
| 4 | Section 5. The Public Construction Bond Act is amended by | ||||||||||||||||||||||||
| 5 | changing Section 1 as follows:
| ||||||||||||||||||||||||
| 6 | (30 ILCS 550/1) (from Ch. 29, par. 15)
| ||||||||||||||||||||||||
| 7 | Sec. 1. Except as otherwise provided by this Act, all | ||||||||||||||||||||||||
| 8 | officials, boards,
commissions, or agents of this State in | ||||||||||||||||||||||||
| 9 | making contracts for public work of
any kind costing over | ||||||||||||||||||||||||
| 10 | $50,000 to be performed for the State, and all officials, | ||||||||||||||||||||||||
| 11 | boards, commissions, or agents of any political subdivision of | ||||||||||||||||||||||||
| 12 | this State in making contracts for public work of any kind | ||||||||||||||||||||||||
| 13 | costing over $5,000 to be performed for the political | ||||||||||||||||||||||||
| 14 | subdivision,
shall require every contractor for the work to | ||||||||||||||||||||||||
| 15 | furnish, supply and deliver
a bond to the State, or to the | ||||||||||||||||||||||||
| 16 | political subdivision thereof entering into
the contract, as | ||||||||||||||||||||||||
| 17 | the case may be, with good and sufficient sureties. The
amount | ||||||||||||||||||||||||
| 18 | of the bond shall be fixed by the officials, boards, | ||||||||||||||||||||||||
| 19 | commissions,
commissioners or agents, and the bond, among other | ||||||||||||||||||||||||
| 20 | conditions,
shall be
conditioned for the completion of the | ||||||||||||||||||||||||
| 21 | contract, for the payment of material
used in the work and for | ||||||||||||||||||||||||
| 22 | all labor performed in the work, whether by
subcontractor or | ||||||||||||||||||||||||
| 23 | otherwise.
| ||||||||||||||||||||||||
| |||||||
| |||||||
| 1 | If the contract is for emergency repairs as provided in the | ||||||
| 2 | Illinois
Procurement
Code, proof of payment for all labor, | ||||||
| 3 | materials, apparatus, fixtures, and
machinery may be
furnished | ||||||
| 4 | in lieu of the bond required by this Section.
| ||||||
| 5 | Each such bond is deemed to contain the following | ||||||
| 6 | provisions whether
such provisions are inserted in such bond or | ||||||
| 7 | not:
| ||||||
| 8 | "The principal and sureties on this bond agree that all the
| ||||||
| 9 | undertakings, covenants, terms, conditions and agreements of | ||||||
| 10 | the contract
or contracts entered into between the principal | ||||||
| 11 | and the State or any
political subdivision thereof will be | ||||||
| 12 | performed and fulfilled and to pay
all persons, firms and | ||||||
| 13 | corporations having contracts with the principal or
with | ||||||
| 14 | subcontractors, all just claims due them under the provisions | ||||||
| 15 | of such
contracts for labor performed or materials furnished in | ||||||
| 16 | the performance of
the contract on account of which this bond | ||||||
| 17 | is given, when such claims are
not satisfied out of the | ||||||
| 18 | contract price of the contract on account of which
this bond is | ||||||
| 19 | given, after final settlement between the officer, board,
| ||||||
| 20 | commission or agent of the State or of any political | ||||||
| 21 | subdivision thereof
and the principal has been made. | ||||||
| 22 | Each bond securing contracts between the Capital | ||||||
| 23 | Development Board or any board of a public institution of | ||||||
| 24 | higher education and a contractor shall contain the following | ||||||
| 25 | provisions, whether the provisions are inserted in the bond or | ||||||
| 26 | not: | ||||||
| |||||||
| |||||||
| 1 | "Upon the default of the principal with respect to | ||||||
| 2 | undertakings, covenants, terms, conditions, and agreements, | ||||||
| 3 | the termination of the contractor's right to proceed with the | ||||||
| 4 | work, and written notice of that default and termination by the | ||||||
| 5 | State or any political subdivision to the surety ("Notice"), | ||||||
| 6 | the surety shall promptly remedy the default by taking one of | ||||||
| 7 | the following actions: | ||||||
| 8 | (1) The surety shall complete the work pursuant to a | ||||||
| 9 | written takeover agreement, using a completing contractor | ||||||
| 10 | jointly selected by the surety and the State or any | ||||||
| 11 | political subdivision; or | ||||||
| 12 | (2) The surety shall pay a sum of money to the obligee, | ||||||
| 13 | up to the penal sum of the bond, that represents the | ||||||
| 14 | reasonable cost to complete the work that exceeds the | ||||||
| 15 | unpaid balance of the contract sum. | ||||||
| 16 | The surety shall respond to the Notice within 15 working | ||||||
| 17 | days of receipt indicating the course of action that it intends | ||||||
| 18 | to take or advising that it requires more time to investigate | ||||||
| 19 | the default and select a course of action. If the surety | ||||||
| 20 | requires more than 15 working days to investigate the default | ||||||
| 21 | and select a course of action or if the surety elects to | ||||||
| 22 | complete the work with a completing contractor that is not | ||||||
| 23 | prepared to commence performance within 15 working days after | ||||||
| 24 | receipt of Notice, and if the State or any political | ||||||
| 25 | subdivision determines it is in the best interest of the State | ||||||
| 26 | to maintain the progress of the work, the State or any | ||||||
| |||||||
| |||||||
| 1 | political subdivision may continue to work until the completing | ||||||
| 2 | contractor is prepared to commence performance. Unless | ||||||
| 3 | otherwise agreed to by the procuring agency, in no case may the | ||||||
| 4 | surety take longer than 30 working days to advise the State or | ||||||
| 5 | political subdivision on the course of action it intends to | ||||||
| 6 | take. The surety shall be liable for reasonable costs incurred | ||||||
| 7 | by the State or any political subdivision to maintain the | ||||||
| 8 | progress to the extent the costs exceed the unpaid balance of | ||||||
| 9 | the contract sum, subject to the penal sum of the bond.".
| ||||||
| 10 | The surety bond required by this Section may be acquired | ||||||
| 11 | from the
company, agent or broker of the contractor's choice. | ||||||
| 12 | The bond and sureties
shall
be subject to the right of | ||||||
| 13 | reasonable approval or disapproval, including
suspension, by | ||||||
| 14 | the State or political subdivision thereof concerned. In the
| ||||||
| 15 | case of State construction contracts, a contractor shall not be | ||||||
| 16 | required to
post a cash bond or letter of credit in addition to | ||||||
| 17 | or as a substitute for the
surety bond required by this | ||||||
| 18 | Section.
| ||||||
| 19 | When other than motor fuel tax funds, federal-aid funds, or | ||||||
| 20 | other
funds received from the State are used, a political | ||||||
| 21 | subdivision may allow
the contractor to provide a | ||||||
| 22 | non-diminishing irrevocable bank letter of
credit, in lieu of | ||||||
| 23 | the bond required by this Section, on contracts under
$100,000 | ||||||
| 24 | to comply with the requirements of this Section. Any such bank
| ||||||
| 25 | letter of credit shall contain all provisions required for | ||||||
| 26 | bonds by this
Section.
| ||||||
| |||||||
| |||||||
| 1 | Notwithstanding this or any other law, in order to promote | ||||||
| 2 | business competition and the stability and growth of small | ||||||
| 3 | businesses, any public body subject to this Act may waive or | ||||||
| 4 | lower the required amount of a surety bond under this or any | ||||||
| 5 | other Act for a public construction contract if the contractor | ||||||
| 6 | is a small business enterprise. As used in this Section, a | ||||||
| 7 | "small business enterprise" means a construction business | ||||||
| 8 | whose annual sales and receipts do not exceed $10,000,000 and | ||||||
| 9 | that is otherwise a small business as defined by rule of the | ||||||
| 10 | Department of Central Management Services under subsection (b) | ||||||
| 11 | of Section 45-45 of the Illinois Procurement Code.
| ||||||
| 12 | (Source: P.A. 95-1011, eff. 12-15-08.)
| ||||||