Sen. Bill Cunningham

Filed: 5/6/2026

 

 


 

 


 
10400SB3273sam001LRB104 18411 AAS 37510 a

1
AMENDMENT TO SENATE BILL 3273

2    AMENDMENT NO. ______. Amend Senate Bill 3273 on page 1,
3line 5, by replacing "Sections 16-107.5 and 17-900" with
4"Section 16-107.5 and by adding Section 17-1000"; and
 
5by replacing line 24 on page 14 through line 6 on page 16 with
6the following:
7    "(h-7) After an electric distribution company determines
8that an interconnection request from an applicant for a public
9school project has been completed, the electric distribution
10company must immediately begin all evaluations, reviews, and
11screenings of the interconnection request. Projects pending in
12the interconnection queue on the same feeder and substation as
13an interconnection request for a public school project shall
14be paused until the public school project has received a fully
15executed interconnection agreement, regardless of queue
16position assignments under 83 Ill. Adm. Code 466, to ensure
17that available feeder and substation capacity is reserved for

 

 

10400SB3273sam001- 2 -LRB104 18411 AAS 37510 a

1the public school project. If the electric distribution
2company determines that there is no requirement for the
3construction of facilities by the electric distribution
4company on its own system, the electric distribution company
5shall provide the applicant with an interconnection agreement,
6as provided under 83 Ill. Adm. Code 466. If the electric
7distribution company determines that the public school project
8has a nameplate capacity that is less than 500 kilowatts (kW)
9with no colocated distribution resources and determines that
10no system modifications are required, the electric
11distribution company must complete all required
12interconnection-related evaluations, reviews, and screenings
13within 30 days after making such a determination and issue an
14interconnection agreement as soon as possible after the
15evaluations, reviews, and screenings are completed. If the
16electric distribution company determines that only minor
17system modifications are required, the electric distribution
18company shall provide the applicant with an interconnection
19agreement within 60 days after the applicant elects to
20continue the application and pays any necessary fees or costs
21required under 83 Ill. Adm. Code 466. If the electric
22distribution company determines that more than minor
23modifications are required, the electric distribution company
24shall provide the applicant with an interconnection agreement
25within 90 days after the applicant elects to continue the
26application and pays any necessary fees or costs required

 

 

10400SB3273sam001- 3 -LRB104 18411 AAS 37510 a

1under 83 Ill. Adm. Code 466."; and
 
2on page 16, line 7, before "or", by inserting "earned on a
3monthly basis"; and
 
4on page 16, line 22, after "Commission", by inserting "serving
5more than 100,000 customers in this State"; and
 
6on page 16, immediately below line 25, by inserting the
7following:
8    ""Public school project" means a renewable electrical
9generating facility that is located on the premises of a
10public school on the customer's side of the billing meter, is
11intended primarily to offset the customer's current or future
12electrical requirements, and is eligible only for renewable
13energy credits apportioned to distributed renewable generation
14devices installed on public school land under subparagraph
15(iv) of paragraph (K) of subsection (c) of Section 1-75 of the
16Illinois Power Agency Act."; and
 
17by replacing line 14 on page 63 through line 6 on page 70 with
18the following:
 
19    "(220 ILCS 5/17-1000 new)
20    Sec. 17-1000. Interconnection application fees for public
21schools. A municipal system or electric cooperative shall not

 

 

10400SB3273sam001- 4 -LRB104 18411 AAS 37510 a

1charge an application fee to a public school for the
2interconnection of renewable generating facilities located on
3the public school's land to the local distribution system that
4exceeds more than 150% of the cost authorized by law or by rule
5to be recovered from customers by public utilities for the
6same or similarly sized facilities with the same or similar
7electric configurations to the local distribution system. An
8interconnection application fee shall be in addition to
9inspection fees or costs, municipal building permit fees, and
10other normal fees charged by municipalities for governmental
11considerations related to non-electric utilities. The limit on
12an interconnection application fee under this Section does not
13apply to any required reimbursement by a public school of the
14cost of any reasonably required metering equipment, system
15impact studies, or system upgrades, which shall be limited to
16actual costs reasonably incurred.".