				    (30 ILCS 557/15)
				
		
		    Sec. 15. 
		Arbitration. 
		A contractor and governmental entity may, by
mutual
agreement, arbitrate the contractor's entitlement to recover the actual
increase in contract
time or costs incurred because of a physical condition at the site.  The
judgment rendered
may be entered in any court having jurisdiction over the matter.
		(Source: P.A. 91-647, eff. 11-30-99.)
	
 |