TITLE 44: GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
SUBTITLE B: SUPPLEMENTAL PROCUREMENT
CHAPTER XII: CAPITAL DEVELOPMENT BOARD
PART 950 PREQUALIFICATION AND BIDDER RESPONSIBILITY
SUBPART A: BIDDER RESPONSIBILITY
Section 950.110 Purpose
Section 950.120 Policy
Section 950.130 Definitions
Section 950.140 Special Projects
Section 950.150 Confidentiality
Section 950.160 Sources for Determining Responsibility
Section 950.170 Processing of Contractor Prequalification and Bidder Responsibility and Renewal Applications
Section 950.180 Ineligibility
SUBPART B: SUSPENSION, DEBARMENT, MODIFICATION OF ABILITY TO BID, AND CONDITIONAL PREQUALIFICATION
Section 950.200 Actions Affecting Prequalification
Section 950.210 Causes for Suspension, Debarment, Modification of Ability to Bid, or Conditional Prequalification
Section 950.220 Failure to Satisfactorily Perform Work on or Breach of the Terms of CDB Contracts, Private Contracts, or Other Governmental Contracts
Section 950.230 Interim or Emergency Suspension or Modification Pursuant to Section 16 of the Capital Development Board Act
Section 950.240 Denial of Prequalification
Section 950.250 Increase or Decrease of Financial Prequalification Rating (Repealed)
Section 950.260 Aggregate Dollar Amount of Contracts (Repealed)
Section 950.270 Contracts More than Seventy Percent (70%) Completed (Repealed)
Section 950.280 Joint Ventures (Repealed)
Section 950.290 Appeal of Prequalification Rating (Repealed)
SUBPART C: APPLICATION OF CDB ACTION
Section 950.300 General
Section 950.310 Violation of CDB Order
Section 950.320 Nullification of Prequalification
Section 950.330 Denial of Award of Contract
Section 950.340 Debarment
Section 950.350 Reapplication for Prequalification
Section 950.360 Extension of CDB Action
Section 950.370 Effect on Current Contracts
Section 950.380 Basis of Decisions
Section 950.390 Settlement
SUBPART D: PROCEDURES
Section 950.400 Review
Section 950.410 Conference
Section 950.420 Executive Director
Section 950.430 Request for Reconsideration
Section 950.440 Hearings
Section 950.450 Burden of Proof
AUTHORITY: Implementing and authorized by Section 9.06 of the Capital Development Board Act [20 ILCS 3105/9.06] and Sections 5-25 and 30-20 of the Illinois Procurement Code [30 ILCS 500/5-25 and 30-20].
SOURCE: Adopted at 2 Ill. Reg. 30, p. 140, effective July 27, 1978; amended at 4 Ill. Reg. 9, p. 233, effective February 14, 1980; amended at 5 Ill. Reg. 1890, effective February 17, 1981; amended and codified at 8 Ill. Reg. 20299, effective October 1, 1984; emergency amendment at 9 Ill. Reg. 3821, effective March 5, 1985, for a maximum of 150 days; amended at 9 Ill. Reg. 10659, effective July 3, 1985; amended at 9 Ill. Reg. 17321, effective October 29, 1985; amended at 12 Ill. Reg. 9860, effective May 27, 1988; amended at 16 Ill. Reg. 12424, effective July 28, 1992; Part repealed, new Part adopted at 19 Ill. Reg. 15607, effective November 2, 1995; amended at 20 Ill. Reg. 15222, effective November 15, 1996; amended at 22 Ill. Reg. 20007, effective November 9, 1998; amended at 25 Ill. Reg. 10741, effective August 10, 2001; amended at 28 Ill. Reg. 4857, effective March 4, 2004; recodified Title of the Part at 39 Ill. Reg. 5903.
SUBPART A: BIDDER RESPONSIBILITY
Section 950.110 Purpose
The Capital Development Board (CDB) contracts shall be awarded only to responsible contractors. A prospective contractor must affirmatively demonstrate its responsibility, including, when necessary, the responsibility of its proposed subcontractors and suppliers. In the absence of information clearly indicating that the prospective contractor is responsible, CDB shall make a determination of non-responsibility. Only responsible contractors shall be prequalified, and only prequalified contractors shall be permitted to bid on CDB projects. A determination of nonresponsibility may be made at any time prior to or after award of a contract.
(Source: Amended at 25 Ill. Reg. 10741, effective August 10, 2001)